Piling complete and verified. Pile caps done. Pier columns done. Headstocks completing for pour this week. Abutment fill arriving on site today. Beams in fabrication, delivery around 20 October. Programme is beam-driven from here.
ITP register running live in Procore for Superintendent sign-off. Headstock pre-pour hold point scheduled Tuesday 15 September. Abutment pre-pour hold point booked for 28 September. Bridge bearings in manufacture in Malaysia, delivery to Georgetown expected in October.
No incidents or near misses this period. Daily toolbox talks and sign-ons completed and audited. An independent safety and environmental audit is planned around beam placement in mid to late October.
Erosion and sediment controls in place. No environmental events this period. Dewatering and spoil management actively controlled ahead of the pour.
Road remains closed to through traffic. Detour signage maintained on both approaches. No open community enquiries. Council's Mayor and Director visited site and noted good progress.
Headstocks are completing and will pour this week. Abutment fill is arriving on site. The bridge is out of the ground and substructure is well advanced. Work off site continues in parallel: precast beams are in fabrication, bearings are in manufacture in Malaysia, and deck and barrier steel is on order. Beam delivery around 20 October is the critical date the rest of the programme runs off.
On site, July to September 2026.
What residents and stakeholders can expect over the next two weeks.
Residents and business owners can register to receive notifications about upcoming works, road closure dates and access changes.
Register for updates →