Pre-construction tracking to plan. Site mobilisation confirmed for 22 June 2026.
ITPs drafted; concrete mix designs and shop drawings under designer review.
WHS Plan and SWMS pack received. Site-based reporting commences at mobilisation.
Environmental Control Plan received. Erosion & sediment controls to be installed at mobilisation.
Stakeholder engagement letters and public notice with Council for distribution.
Pre-construction activities are progressing to plan. Procurement, design, subcontracting and stakeholder engagement workstreams are all in flight ahead of site mobilisation on 22 June 2026.
What residents and stakeholders can expect, and where.
Residents and business owners can register to receive notifications about upcoming works, road closure dates and access changes.
Register for updates →